Miller Act: when you need payment and performance bonds
BondsSource: FAR 28.102-1 General. (48 CFR) (eCFR, current as of 2026-11-10)
Federal construction contracts over $150,000 require both a performance bond and a payment bond.
For contracts over $35,000 up to $150,000, the contracting officer selects two or more payment protections (payment
bond,
irrevocable letter of credit, tripartite escrow agreement, certificates of deposit, or other listed security).
- Official text quoted word for word
- eCFR as of 2026-11-10

What the rule says
“requires performance and payment bonds for any construction contract exceeding $150,000”
FAR 28.102-1 General. (48 CFR) · eCFR, current as of 2026-11-10
“for construction contracts greater than $35,000, but not greater than $150,000,
the contracting officer shall select two or more of the following payment protections”
FAR 28.102-1 General. (48 CFR) · eCFR, current as of 2026-11-10
Step by step
- Size the contractOver $150,000: both bonds. $35,000-$150,000: alternatives chosen by the contracting officer.
- Line up surety capacity earlyBond capacity limits how many jobs you can bid at once.
- Check state jobs separatelyState and local public works use the state's 'Little Miller Act', with different thresholds.
Worked example: three contract sizes
| $1,200,000 federal construction contract | Performance bond + payment bond |
|---|---|
| $90,000 | Two or more payment protections chosen by the contracting officer |
| $30,000 | Not covered by these bond rules |
Common mistakes
- Assuming state thresholds match the federal $150,000 line.
On state-funded jobs. State and local jobs follow "Little Miller Acts", with their own lines: Texas requires a performance bond over $100,000 and a payment bond over $25,000 (Government Code ch. 2253); Pennsylvania local governments require bonds from $10,000 (Act 86 of 2020), and Commonwealth agencies use $70,318 and $281,273 (62 Pa.C.S. § 903, as adjusted January 1, 2026).
Limits. This guide — Miller Act: when you need payment and performance bonds — quotes the federal rule from the sources below. It is not a substitute for the wage determination or the clause in your contract. State law can be stricter; see the note on state-funded jobs. Worked examples and calculator defaults use the wage determination named on the page, as of the date shown there.
Related
Sources
- FAR 28.102-1 General. (48 CFR) — eCFR, current as of 2026-11-10