Bid bond on a federal construction bid: how much, and when
BondsSource: FAR 28.101-1 Policy on use. (48 CFR) (eCFR, current as of 2026-11-10)
On federal construction, a bid guarantee (usually a bid bond)
is required whenever the contract needs a performance bond, which means contracts over $150,000.
Its amount is at least 20% of your bid price and the contracting officer cannot ask for more than $3 million.
In sealed bidding, a missing or short bid guarantee normally gets the bid rejected,
except in the cases where FAR 28.101-4(c)
says it shall be waived.
Check which bonds your contract size needs →
- Official text quoted word for word
- eCFR as of 2026-11-10

What the rule says
“A contracting officer shall not require a bid guarantee unless a performance bond or a performance
and payment bond is also required (see 28.102 and 28.103).”
FAR 28.101-1 Policy on use. (48 CFR) · eCFR, current as of 2026-11-10
“Only separate bid guarantees are acceptable in connection with construction contracts.”
FAR 28.101-1 Policy on use. (48 CFR) · eCFR, current as of 2026-11-10
“The bid guarantee amount shall be at least 20 percent of the bid price but shall not exceed $3
million.”
FAR 28.101-2 Solicitation provision or contract clause. (48 CFR) · eCFR, current as of 2026-11-10
“In sealed bidding, noncompliance with a solicitation requirement for a bid guarantee requires
rejection of the bid”
FAR 28.101-4 Noncompliance with bid guarantee requirements. (48 CFR) · eCFR, current as of 2026-11-10
“Noncompliance with a solicitation requirement for a bid guarantee shall be waived in the following
circumstances unless the contracting officer determines in writing that acceptance of the bid would
be detrimental to the Government's interest when—”
FAR 28.101-4 Noncompliance with bid guarantee requirements. (48 CFR) · eCFR, current as of 2026-11-10
“The amount of the bid guarantee submitted is less than required,
but is equal to or greater than the difference between the offer price and the next higher
acceptable offer;”
FAR 28.101-4 Noncompliance with bid guarantee requirements. (48 CFR) · eCFR, current as of 2026-11-10
“An otherwise acceptable bid bond was submitted with a signed offer,
but the bid bond was not signed by the offeror;”
FAR 28.101-4 Noncompliance with bid guarantee requirements. (48 CFR) · eCFR, current as of 2026-11-10
“An otherwise acceptable bid bond is erroneously dated or bears no date at all; or”
FAR 28.101-4 Noncompliance with bid guarantee requirements. (48 CFR) · eCFR, current as of 2026-11-10
Step by step
- Check whether a performance bond is requiredOver $150,000 on federal construction: yes, so a bid guarantee is required too (unless the chief of the contracting office waived it).
- Compute the amount20% of your bid price, or the amount the solicitation states; never more than $3 million.
- Use a separate guaranteeOn construction, an annual bid bond does not count: the guarantee must be for this bid.
- Check signatures and datesIf an otherwise acceptable bid bond was not signed by the offeror, or is wrongly dated or undated, FAR 28.101-4(c) says the noncompliance shall be waived, unless the contracting officer determines in writing that accepting the bid would hurt the Government. A short guarantee is also waived when it covers at least the gap to the next higher acceptable offer. Sign and date it anyway.
Worked example: minimum bid guarantee for three federal construction bids
| Bid price | Minimum bid guarantee |
|---|---|
| $120,000.00 | Not required by FAR 28.101 (no performance bond at this size) |
| $450,000.00 | $90,000.00 (20% of the bid) |
| $20,000,000.00 | $3,000,000.00 (20% would be $4,000,000.00; capped at $3 million) |
The solicitation can state a higher amount or a percentage with a dollar cap; it is never more than $3 million.
- Sending an annual bid bond on a construction bid.
- Pricing the bid guarantee on the base bid only when the solicitation asks for the total including options.
- Missing the bid guarantee and expecting a correction after bid opening.
Related
Bond premium estimator
Public works bonds
Miller Act: when you need payment and performance bonds
Bid cost calculator: one number for the whole crew
Sources
- FAR 28.101-1 Policy on use. (48 CFR) — eCFR, current as of 2026-11-10
- FAR 28.101-2 Solicitation provision or contract clause. (48 CFR) — eCFR, current as of 2026-11-10
- FAR 28.101-4 Noncompliance with bid guarantee requirements. (48 CFR) — eCFR, current as of 2026-11-10